Hardware Installations and Upgrades
Intel
®
Server System R2000BB Service Guide 63
5. Fasten the four screws to secure the storage front panel (see letter “E”).
Figure 100. Installing the storage front panel
Removing the Storage Front Panel
1. Remove the four screws to release the storage front panel (see letter “A”);
2. Remove the storage front panel from the rack handle (see letter “B”);
Figure 101. Installing the storage front panel
3. Disconnect all the cables from the interposer card (see letter “C”);
4. Remove the two screws to release the storage front panel (see letter “D”);
5. Remove the storage front panel from the side wall of server chassis (see letter “E”);